  • Превод МК Detailed Design for construction of Wind Park Budakovo (50 MW)
    • SS 35/110 kV WP Budakovo
    • 2×110 kV OHL WP Budakovo – 110 kV OHL Theranda – Ferizaj (in-out)
    • 35 kV internal MV and FOC network
    • Electromechanical design
    • Construction-civil design
    • Ordered by: KOSTT/Elektra Kosovo
    • 2021 – Under progress
  • Main Design for construction of Wind Park WP Euroing (30 MW)
    • SS 33/110 kV WP Euroing
    • 2×110 kV OHL WP Euroing – SS Gevgelija
    • 33 kV internal MV and FOC network
    • Internal roads
    • Electromechanical design
    • Construction-civil design
    • Ordered by: Euroing Gevgelija
    • 2019
  • Main Design for construction of WP Demir Kapija (Dren) (34 MW)
    • SS 33/110 kV WP Demir Kapija
    • 110 kV OHL WP Dren – SS Dubrovo
    • 33 kV internal MV and FOC network
    • 110 kV OHL bay in SS Dubrovo
    • Internal roads
    • Electromechanical design
    • Construction-civil design
    • Ordered by: Kaltun Energy Turkey
    • 2019-2020
  • Detailed Design for construction of SS 33/110kV WP Bogoslovec
    • Electromechanical design – Wiring diagrams
    • Construction-civil design
    • Ordered by: Hitachi ABB Croatia
    • 2020-2021
  • Main Design for construction of WP Bogoslovec (36 MW)
    • SS 33/110 kV WP Bogoslovec
    • 2×110 kV OHL WP Bogosovec – 110 kV OHL Stip – Ovce Pole (in-out)
    • 33 kV internal MV and FOC network
    • Internal roads
    • Electromechanical design
    • Construction-civil design
    • Ordered by: THOR Impeks Skopje
    • 2016-2018