Main design for construction of 35 kV cable line for connection of PVPP Samokov (10MWp), L=4,5 km
Ordered by: EVN Macedonia
Year: 2021
Main design for construction of 110 kV cable line SS Jug Nova -SS Centralna, L=2,9 km
Ordered by: EVN Macedonia
Year: 2019
Main design for construction of 35 kV cable line SS 110/35/10 kV Tetovo 1 – HPP Pena, L=3.7 km
Ordered by: EVN Macedonia
Year: 2019
Main design for construction of 35 kV cable line SS 110/35/10 kV Tetovo 1 – SS Tetovo, L=3.6 km
Ordered by: EVN Macedonia
Year: 2019
Main design for construction of 35 kV cable line SS 35/10 kV Saraj – SS 35/10kV Kondovo, L=2.4 km
Ordered by: EVN Macedonia
Year: 2018
Main design for construction of 110 kV OHTL SS Shtip – SS Probishtip, L=25 km
Ordered by: NDREKAJ Construction R.Albania-subsidiary Skopje
Year: 2018
Main design for 400 kV OHTL SS Bitola 2 – SS Ohrid – Macedonian/Albanian border, L=98km
Ordered by: Fichtner/ GEING Krebs und Kiefer International – Skopje
Year: 2017
Main design for 2×110 kV OHTL for connection of SS in WP Bogoslovec, L=4,9 km
Ordered by: THOR impex Skopje
Year: 2017
Main design for 110 kV OHTL Berivojica – Kitka, R. Kosovo, L=14,8 km
Ordered by: Elektra Kosovo
Year: 2017
Main design for relocation of section of 2х110 kV OHTL SS Skopje 1 – SS Gazi Baba and OHTL SS Skopje 1 – SS Vasil Glavinov
Ordered by: EVN Macedonia
Year: 2016
Main design for construction of 20 kV OHL SS 35/10(20)kV Demir Kapija – SS 10(20)/0,4kV Tunnel Т1 Local control station, L=3,9 km
Ordered by: Public enterprise for state roads Skopje
Year: 2016
Main design for construction of 20 kV combined cable and OH line from SS 35/10(20) kV Udovo to junction point at km 15+680 for SS 10(20)/0,4 kV Tunnel Т1 North, L=6 km
Ordered by: Public enterprise for state roads Skopje
Year: 2016
Main design for relocation of section of 400 kV OHTL „SS Dubrovo – Macedonian/Greek border“ from tower no.90 to tower no.94 due to crossing with new motorway А1 “Demir Kapija – Smokvica” at km.22+850, L=2 km
Investor: Public enterprise for state roads Skopje Ordered by: Aktor ADT Greece – Subsidiary Skopje
Year: 2015
Technical documentation for Reconstruction of existing OHTL 35 kV SS 110/35/10kV „Ohrid 1“- SS 35/10kV „Kosel“ from tower no.2 to tower no.43, L=4 km
Ordered by: EVN Macedonia
Year: 2015
Main design for construction of 2х35kV cable line SS 110/35/10 kV “Bitola 3” – SS 35/10kV “Termo”, L=4 km
Ordered by: EVN Macedonia
Year: 2015
Main design for construction of 35kV cable line SS 110/35/10 kV Kicevo – SS 35/10 kV Izvor, L=11 km
Ordered by: EVN Macedonia
Year: 2015
Main design for 10(20)kV OHTL for connection of SHPP “125” to TSS 10(20)/0,4 kV “village Lipkovo”, L=3.4 km
Ordered by: SOL Hydropower Skopje
Year: 2014
Preliminary design for construction of 110kV OHTL “SS 110/35/10 kV Kichevo – SS 35/10 kV Izvor” (replacement of existing 110kV OHTL “SS 110/35/10 kV Kichevo – SS 35/10 kV Izvor” due to construction of motorway А2 – section Kichevo – Trebenishta)
Ordered by: EVN Macedonia
Year: 2014
Main design for Reconstruction of 110 kV OHTL no. 105/1 SS “Veles” – SS “Ovche Pole”, L=21 km
Ordered by: AD MEPSO
Year: 2013
Main design for Reconstruction of 110 kV OHTL no. 105/2 SS “Ovche Pole” – SS “Shtip”, L=17,9
Ordered by: AD MEPSO
Year: 2013
Main design for Reconstruction of 110 kV OHTL no. 116 SS “Shtip” – SS “Probishtip”, L=25 km
Ordered by: AD MEPSO
Year: 2013
Main design for Reconstruction of 110 kV OHTL no. 101/2 SS “Skopje 4” – SS “Veles”, L=31,6 km
(section from Jurumleri tower no. 23 – SS “Petrovec”)
(section SS “Petrovec” – SS “Veles”)
Ordered by: AD MEPSO
Year: 2013
As built design for reconstruction of 110 kV OHTL “HPP Sv. Petka – SS Skopje 3” (from new angle-tension tower no. 154/2 to SS Skopje 3): appliance of new type of conductor and replacement of grounding wire with OPGW, L=15,6 km
Ordered by ENERGOMONTAZA, Belgrade
Year: 2012
As built design for 110 kV OHTL “HPP Sv. Petka – HPP Kozjak” (from new angle-tension tower no. 154/1 to HPP Kozjak): replacement of grounding wire, L=6,9 km
Ordered by ENERGOMONTAZA, Belgrade
Year: 2012
As built design for 110(35) kV OHTL “SS Kavadarci 1 – SS Kavadarci Gradska”, L=1,8 km
Ordered by MEPOS-Kavadarci
Year: 2012
Main Design for 110 kV OHTL for connection of SS Wind park “Bogdanci” and SS “Valandovo”, L=10,8 km
Ordered by ELNOS Banja Luka
Year: 2012
As built design for 2×110 kV connecting OHTL on HPP “Sveta Petka” toward 110kV OHTL “HPP Kozjak-SS Skopje 3”, L=2,9 km
Ordered by ELNOS-Banja Luka, ENERGOMONTAZA Belgrade (electrical part)
Ordered by DASS engineering-Ohrid (civil part)
Year: 2012
As built Design for 110 kV OHTL for connection of SS 6/35/110kV “Arremolle” and SS 110/10kV “Kurbnesh” – R. Albania, L=16,2 km
Ordered by YUNIG Ltd. Export-Import & Engineering, Ohrid, Macedonia
Year: 2012
Main Design for new 20 kV OHTL for connection of HPP Lura 3 with HPP Lura 1-2, R. Albania, L=3,5 km
Ordered by YUNIG Ltd. Export-Import & Engineering, Ohrid, Macedonia
Year: 2012
Preliminary route & Detail design for 2×132 kV transmission line SS “Old Abeokuta”-SS “Papalanto” L=31 km
Ordered by Chris Ejik International Agencies Ltd, Lagos Nigeria
Year: 2008-2012
Preliminary route & Detail design for 2×132 kV transmission line SS “Old Abeokuta”-SS “New Abeokuta” L=8km
Ordered by Chris Ejik International Agencies Ltd, Lagos Nigeria
Year: 2008-2012
Preliminary route & Detail design for 2×132 kV transmission line SS “Papalanto”-SS “Otta” L=36 km
Ordered by Chris Ejik International Agencies Ltd, Lagos Nigeria
Year: 2012
Main design for reconstruction of 110 kV OHTL “HPP St. Petka-SS Skopje 3” (from new angle-tension tower no. 154/2 to SS Skopje 3) for replacement of conductor and for replacement of classic grounding wire with OPGW
Ordered by JSC MEPSO
Year: 2011
Main design for 110 kV OHTL “HPP Kozjak-SS Skopje 3” (from new angle-tension tower no. 154/1 to HPP Kozjak) for replacement of classic grounding wire with OPGW
Ordered by JSC MEPSO
Year: 2011
Main design for 2×110 kV connecting OHTL on power plant HPP Sveta Petka toward 110 kV OHTL “HPP Kozjak-SS Skopje 3” , L=2,9 km
Ordered by JSC ELEM-Subsidiary HPP Treska
Year: 2011
Detail Design for 110 kV OHTL for connection of HPP-SS “Lapaj” and SS 110/10 kV “Kukes” – R. Albania, L=22,2 km
Ordered by DASS engineering-Ohrid
Year: 2011
Detail Design for 110 kV OHTL for connection of SS 6/35/110kV “Arremolle” and SS 110/10 kV “Kurbnesh” – R. Albania, L=16,2 km
Ordered by DASS engineering-Ohrid
Year: 2011
Main Design for reconstruction (cable connection) of 110 kV OHTL No. 118/2 “Prishtine 1 – Prishtine 4” between towers No. 7 and 8
Ordered by YUNIG Ltd. Export-Import & Engineering, Ohrid, Macedonia
Year: 2011
As built design for 110 kV interconnection of combined heat and power plant TE-TO (in-out)2×110 kV Overhead transmission line & 2×110 kV cable line, L=2,1 km TL; L=3,8 km cable
Ordered by Dalekovod-Subsidiary Skopje
Year: 2011
Basic, Detail & As built Design for relocation of towers no.(3) and (4) of 110 kV Overhead transmission line 118/3 SS Ferizaj – SS 110/6 kV “Sharrcem” (Hani i Elezit),
Orderd by Yunig engineering-Ohrid for Sharrcem, Hani i Elezit, Kosovo
Year: 2010
Basic, Detail & As built Design for relocation of tower no.(2A) and (3A) of 110 kV Overhead transmission line Gilane – SS 110/6 kV “Sharrcem” (Hani i Elezit)
Orderd by Yunig engineering-Ohrid for Sharrcem, Hani i Elezit, Kosovo
Year: 2010
Basic and Detail design for 110 kV interconnection of combined heat and power plant TE-TO (in-out)2x110kV Overhead transmission line & 2×110 kV cable, L=2,1 km TL; L=3,8 km cable
Ordered by Korona-Ljubljana, R. Slovenia
Year: 2009
Detail design for 35 kV cable line “SS Berovo-SS Pehcevo”, L=9,2 km
Ordered by EVN Macedonia
Year: 2008
Detail design for 35 kV cable line “SS 110/35kV Bitola 1 – SS 35/0,4kV Sokomak”, L=2,7 km
Ordered by EVN Macedonia
Year: 2008
Detail design for 35 kV cable line “SS 35/10kV HPP Matka – SS 35/10kV Saraj”, L=7,6 km
Ordered by EVN Macedonia
Year: 2008
Detail design for 20(10) kV cable line “SS 35/10kV Saraj – SS 10/0,4kV Saraj 1”, L=1,6 km
Ordered by EVN Macedonia
Year: 2008
Detail design for 110 kV Overhead transmission line “Skopje-Kumanovo”, L=25,5km
Replacement of classic grounding wire with optical grounding wire
Ordered by AD Mepso
Year: 2007
Detail design for 110 kV Overhead transmission line “Kumanovo-Kratovo”, L=33,2km
Replacement of classic grounding wire with optical grounding wire
Ordered by AD Mepso
Year: 2007
Detail design for 110 kV Overhead transmission line “Kratovo-Probistip”, L=16,0 km
Replacement of classic grounding wire with optical grounding wire
Ordered by AD Mepso
Year: 2007
Detail design for 110 kV Overhead transmission line “Oslomej-Gostivar”, L=36,5km
Replacement of classic grounding wire with optical grounding wire
Ordered by AD Mepso
Year: 2007
Detail design for 110 kV Overhead transmission line “Veles 2-Kavadarci 1”
Replacement of classic grounding wire with optical grounding wire,
Ordered by AD Mepso
Year: 2007
Basic & Detail design for 132 kV Overhead transmission line “Ohafia” – “Arochukwu” L=32km (Financed by NEPA Nigeria)