Revision of project documentation for Cable and OH Transmission Lines

  • Revision of Main design for 110kV OHL for SS 110/10 kV IHM Trade
    • Designer: Sinvir Project
    • Investor: IGM Trade
    • Year: 2019
  • Revision of Main design for 110kV cable line SS 110/35/10kV Jug nova – SS 110/35/10kV Centralna (2)
    • Designer: TIMEL project DOOEL – Skopje
    • Investor: EVN Macedonia
    • Year: 2018
  • Revision of Main design for 35kV cable line SS 110/35/10kV „Skopje 1“ – SS 35/10kV „Madzari“
    • Designer: TIMEL project DOOEL – Skopje
    • Investor: EVN Macedonia
    • Year: 2018
  • Revision of Technical solution for temporary operation mode of OHTL 2х110kV SS 110/10kV Vasil Glavinov – SS 110/35/10kV Gazi Baba by connecting OHTL 2х110kV (no.123А) SS 110/35kV Skopje 1 – SS 110/10/6kV Zelezara (system 1)
    • Designer: TIMEL project DOOEL – Skopje
    • Investor: EVN Macedonia
    • Year: 2017
  • Revision of Technical solution for reconstruction of OHTL 150kV SS 110/35/10kV Bitola 1- R.Greece into OHTL 110kV and construction of cable line separation Bitola 1 – Zabeni – Bukri on  new steel lattice tower
    • Designer: TIMEL project DOOEL – Skopje
    • Investor: EVN Macedonia
    • Year: 2017
  • Revision of Main design for cabling of part of existing 35kV OHTL “35kV SY Ovche Pole – SS 35/10kV Sveti Nikole” (from tower no. 35 to tower no. 49)
    • Designer: Timel proekt DOOEL – Skopje
    • Investor: EVN Macedonia
    • Year: 2016
  • Revision of technical documentation for Mounting of grounding wire and reconstruction of grouinding of 35kV OHTL “SS 35/10kV HPP Pesochani – SS 35/10kV Mesheishta”
    • Designer: Timel proekt DOOEL – Skopje
    • Investor: EVN Macedonia
    • Year: 2016
  • Revision of Main design for 35kV cable line “SS 110/35/10kV Skopje 1 – SS 35/10kV Radishani”
    • Designer: Timel proekt DOOEL – Skopje
    • Investor: EVN Macedonia
    • Year: 2016
  • Revision of Main design for 35kV cable line “SS 110/35/10kV Zapad –SS 35/10kV Saraj”
    • Designer: Timel proekt DOOEL – Skopje
    • Investor: EVN Macedonia
    • Year: 2016
  • Revision of Main design for cabling of part of existing OHTL 35kV “SS 110/35/10kV Shtip 1 – SY Ovche Pole” (from tower no. 74 to tower no. 75)
    • Designer: Timel proekt DOOEL – Skopje
    • Investor: EVN Macedonia
    • Year: 2016
  • Revision of Main design for relocation of existing 35kV OHTL “SS 110/35/10kV Shtip 1 – SY Ovche Pole” (from tower no.41 to tower no.49)
    • Designer: Timel proekt DOOEL – Skopje
    • Investor: EVN Macedonia
    • Year: 2016  
  • Revision of Main design for 110kV connection (input-output) of SS 110/35/10kV “Petrovec”
    • Ordered by: AD MEPSO
    • Year: 2014
  • Revision of Main design for 2x110kV OHTL “SS Bitola 3 – SS Bitola 4” (110kV connection to SS Bitola 4)
    • Ordered by: AD MEPSO
    • Year: 2013
  • Revision of Main design for Reconstruction of 110kV OHTL no.109 “SS Bitola 1 – SS Prilep 1”
    • Ordered by: AD MEPSO
    • Year: 2013
  • Revision of Main design for Reconstruction of 2x110kV OHTL no.125 “SS Skopje 1 – SS Miladinovci”
    • Ordered by: AD MEPSO
    • Year: 2013
  • Revision of Main design for replacement of grounding wire type Fe III 70mm2 with OPGW, on 110kV OHTL “SS Samokov-SS Kozjak”
    • Ordered by AD MEPSO
    • Year: 2011-2012
  • Revision of Main design for replacement of grounding wire type Fe III 50mm2 with OPGW, on 110kV OHTL “SS Vrutok-SS Gostivar” – connection on SS Gostivar
    • Ordered by AD MEPSO
    • Year: 2011-2012
  • Revision of Main design for replacement of grounding wire type Fe III 50mm2 with OPGW, on 110kV OHTL “SS Radovish-SS Berovo”
    • Ordered by AD MEPSO
    • Year: 2011-2012
  • Revision of Main design for replacement of grounding wire type Fe III 70mm2 with OPGW, on 2x110kV OHTL “SS Bitola 2-SS Bitola 3”
    • Ordered by AD MEPSO
    • Year: 2011-2012
  • Revision of Main design for replacement of grounding wire type Fe III 50mm2 with OPGW, on 110kV OHTL “SS Dubrovo-SS Valandovo”
    • Ordered by AD MEPSO
    • Year: 2011-2012
  • Revision of Main design for replacement of grounding wire type Fe III 50mm2 with OPGW, on 110kV OHTL – connection to SS Polog
    • Ordered by AD MEPSO
    • Year: 2011-2012
  • Revision of Main design for replacement of grounding wire type Fe III 70mm2 with OPGW, on 110kV OHTL “SS Strumica 1-SS Sushica”
    • Ordered by AD MEPSO
    • Year: 2011-2012
  • Revision of Main design for replacement of grounding wire type Fe III 70mm2 with OPGW, on 110kV OHTL “SS Oslomej-SS Samokov”
    • Ordered by AD MEPSO
    • Year: 2011-2012
  • Revision of Main design for replacement of grounding wire type Fe III 50mm2 with OPGW, on 110kV OHTL “SS Oslomej-SS Kicevo”
    • Ordered by AD MEPSO
    • Year: 2011-2012
  • Revision of Main design for replacement of grounding wire type AWG 19/9 (126,1mm2) with OPGW, on 400kV OHTL “SS Macedonian-Kosovo border-SS Skopje 5”
    • Ordered by AD MEPSO
    • Year: 2011-2012
  • Revision of Main design for replacement of grounding wire type Fe III 50mm2 with OPGW, on 110kV OHTL “SS Skopje 2-SS Skopje 4” (tower no. 7)
    • Ordered by AD MEPSO
    • Year: 2011-2012
  • Revision of Main design for replacement of grounding wire type Fe III 50mm2 with OPGW, on 2x110kV OHTL “SS Ohrid 1-SS Ohrid 2”
    • Ordered by AD MEPSO
    • Year: 2011-2012
  • Revision of Main design for replacement of grounding wire type Fe III 50mm2 with OPGW, on 110kV OHTL “SS Delcevo-SS Berovo”
    • Ordered by AD MEPSO
    • Year: 2011-2012
  • Revision of Main design for replacement of grounding wire type Fe III 50mm2 with OPGW, on 110kV OHTL “SS Makedonska Kamenica-SS Delcevo”
    • Ordered by AD MEPSO
    • Year: 2011-2012
  • Revision of Main design for replacement of grounding wire type Fe III 50mm2 with OPGW, on 110kV OHTL “SS Kochani-SS Makedonska Kamenica”
    • Ordered by AD MEPSO
    • Year: 2011-2012
  • Revision of Main design for replacement of grounding wire type Fe III 50mm2 with OPGW, on 110kV OHTL “SS Strumica 1-SS Strumica 2”
    • Ordered by AD MEPSO
    • Year: 2011-2012
  • Revision of Main design for replacement of grounding wire with OPGW, on 110kV OHTL “SS Skopje 4-SS Skopje 3”
    • Ordered by AD MEPSO
    • Year: 2011-2012
  • Revision of Main design for reconstruction of 110kV OHTL “SS Skopje 1-SS Kumanovo” (replacement of conductor)
    • Ordered by AD MEPSO
    • Year: 2011
  • Revision of Main design for 2x110kV OHTL “SS Bitola 3-SS Bitola 4” (110kV connection to SS Bitola 4)
    • Ordered by AD MEPSO
    • Year: 2010
  • Revision of 2×110 kV Overhead transmission line Vrutok – Tetovo, L=30km
    • Financed by EIB, Ordered by AD MEPSO – Skopje
    • Year: 2005
  • Revision of 110 kV Overhead transmission line Brod – Gneotino, L=11km
    • Financed by KFB bank, Ordered by ELEM – Skopje
    • Year: 2005
  • Revision of 110 kV Overhead transmission line Jurumleri – Skopje-4, L=11km
    • Financed & ordered by AD MEPSO Skopje
    • Year: 2004